Ministry of Foreign Affairs spends ¢7.9m on a ¢1.4m project because contractor fell ill – Chief Director
The Foreign Affairs Ministry said a project that was initially supposed to cost government GH¢1,435,728.99 was executed at GH¢7,967,886.57 because the contractor did not execute on time due to ill health.
The contract for the rehabilitation of Adu Lodge Guest House was awarded to International Development Resources on March 15, 2007.
But according to the Acting Chief Director of the Ministry, Ambassador Ramses Joseph Cleland, the project came to a grind a year later due to the ill health of the contractor.
Appearing before the Public Accounts Committee (PAC) on Friday, January 20, 2023, the Ministry said the project was revisited in March 2019 and upon the request of the consultant, was re-valued to GH¢7,967,886.57 for the same contractor to execute.
The Auditor General’s report noted that, as of June 2019, a total of GH¢7,741,501.60 (representing 90% of the contract sum) had already been paid.
According to the Ministry, the project has finally been completed and handed over to the Ministry, after 13 years of delay.
Unsatisfied with the explanation from the Ministry’s explanation, the committee queried whether the terms of the contract allowed for the inability of the contractor to execute the project in due course, to come at a cost to the state.
The Ministry in response said they were unable to speak to that except the estate officer, who was not present at the committee sitting.
The committee has therefore directed the Ministry to furnish the Public Accounts Committee with the contract and all necessary documents for a determination on the matter in its report.
-
Environment4 weeks ago
Zoomlion, Graphic Clean Koforidua Ahead Of Independence Day Celebrations
-
Insurance2 weeks ago
Trailblazing with Grace: An Interview with Yvonne, C.O.O of Bedrock Insurance on Her Journey through Leadership and Empowerment in the Insurance Industry
-
Environment2 weeks ago
Zoomlion Sets Gold Standard in Waste Management at 2023 All African Games
-
Features and Opinions1 week ago
Empowering Women, Driving Innovation, Leading with Integrity: Kakra Journey to Success
-
Environment2 weeks ago
Zoomlion Supports Buz Stop Boys To Clean Parts of Accra
-
Banking and Finance1 week ago
Interview with Rebecca on Her Journey of Resilience and Inclusion in Ghana’s Microfinance Industry
-
General News4 weeks ago
We don’t have space to accommodate graduates from tertiary institutions – Ghana Employers Association
-
Banking and Finance3 weeks ago
Bank of Ghana Suspends Guaranty Trust Bank, FBNBank over ‘fraudulent documentation’